Custom conveyor design process for system integrators

What a custom conveyor project actually looks like from enquiry to FAT — inputs, drawing stages, approval points and what shortens the timeline.

A custom conveyor project fails or succeeds long before steel is cut — in the first two weeks, when the inputs are either pinned down or left vague. Here is the sequence that keeps a project on schedule.

Inputs the integrator supplies

Product drawing with weight and underside, plant layout with column and height constraints, required takt and buffer size, the utility and control standard you work to, and the drawing standard you want back. A project with those five inputs starts the same week.

Stage 1 — 3D layout proposal (72 h)

BIFA engineers return a 3D layout with module selection, drive positions and operator stations marked, plus a budgetary price. This is the stage where scope changes are cheap; later they cost weeks.

Stage 2 — GA drawings and BOM

On approval, detailed GA drawings, electrical schematics, a BOM and the spare-parts list are issued. Your team reviews interfaces — power, air, network, safety circuits — while the material is ordered.

Stage 3 — Build, FAT and ship

The line is built and wired in Kunshan, then run with your product in an FAT you attend or witness by video. Modules ship in transport sections with matched joints so on-site assembly is bolting, not fitting.

The single biggest schedule risk is a late product sample. Send one early — even a mock-up with the right weight and footprint — and the FAT becomes a formality.

Tell us your load case

Attach a drawing or a short spec — our engineers reply within 72 hours with a layout proposal and budgetary price.

  • 72 h engineering response
  • GA drawing & BOM before production
  • CE · ISO 9001 · COO

Or email us directly at info2@bifaconveyor.com